PRINCE2 PRINCE2-Practitioner Exam Overview:

Certification Vendor:AXELOS / PeopleCert
Exam Name:PRINCE2® Project Management Practitioner (Version 7)
Exam Number:PRINCE2-Practitioner
Passing Score:60% (42 out of 70 marks)
Related Certifications:PMP
PRINCE2 Agile
CAPM
PRINCE2 Foundation
MSP
Exam Duration:150 minutes
Exam Price:$450 - $550 USD / £470 - £520 GBP / €395 - €450 EUR
Available Languages:Portuguese, French, English, Dutch, German, Chinese (Simplified), Japanese, Spanish, Polish, Italian, Arabic
Certificate Validity Period:3 years
Exam Format:Open-book (official PRINCE2 manual only), No negative marking, Multiple-choice, Scenario-based objective test
Real Exam Qty:70
Recommended Training:Official PRINCE2 Training Providers
Exam Registration:PeopleCert Official Registration
Sample Questions: DOWNLOAD DEMO
Exam Way:Online remote proctored exam or authorized test center
Pre Condition:Must hold valid PRINCE2 Foundation (6th or 7th edition), or equivalent: PMP, CAPM, IPMA A-D, or other recognized project management qualifications
Official Syllabus URL:https://www.peoplecert.org/certifications/axelos/prince2/project-management/practitioner

PRINCE2 PRINCE2-Practitioner Exam Syllabus Topics:

SectionWeightObjectives
PRINCE2 Processes25%- Initiating a Project
- Managing a Stage Boundary
- Controlling a Stage
- Starting up a Project
- Closing a Project
- Managing Product Delivery
- Directing a Project
PRINCE2 Principles15%- Tailor to suit the project environment
- Focus on products
- Manage by exception
- Learn from experience
- Continued business justification
- Defined roles and responsibilities
- Manage by stages
PRINCE2 Practices50%- Progress
- Organizing
- Issues
- Plans
- Risk
- Quality
- Business Case
Tailoring PRINCE210%- Integration with other methods
- Adapting to project size, complexity and context
- Tailoring principles, practices and processes

Common Questions About PRINCE2 Practitioner

The PRINCE2-Practitioner exam, PRINCE2 Practitioner Exam, assesses whether a candidate can apply PRINCE2 knowledge to the skills measured by this credential. It is associated with the PRINCE2 Practitioner certification. The certification is positioned at the Practitioner / Professional level. Related credentials include PRINCE2 Foundation, PRINCE2 Agile, MSP, PMP, CAPM.

The PRINCE2-Practitioner exam includes 70 questions and allows 150 minutes. Plan your pacing before exam day rather than calculating it under pressure. Timed sessions with Actual4dump practice tests can help you decide when to flag a difficult item, keep moving, and reserve enough time for a final review.

The published passing score for PRINCE2 Practitioner is 60% (42 out of 70 marks), and the official exam fee is $450 - $550 USD / £470 - £520 GBP / €395 - €450 EUR. A retake requires budgeting for the full official fee again, so it is sensible to complete several timed practice tests before scheduling. Consistent results across the 266 practice questions can give you a clearer picture of your readiness.

The stated prerequisite information for PRINCE2 Practitioner is: Must hold valid PRINCE2 Foundation (6th or 7th edition), or equivalent: PMP, CAPM, IPMA A-D, or other recognized project management qualifications Before registering, review the eligibility details on the official exam page to confirm the requirements.

You can register for PRINCE2 Practitioner through the following channels:

The available exam delivery format is Online remote proctored exam or authorized test center.

The following official training resources are recommended for PRINCE2 Practitioner:

After reviewing these training options, you can reinforce each topic with 266 practice questions from Actual4dump.

Yes. Actual4dump provides a free PDF demo so you can review the format and quality of the PRINCE2 Practitioner practice questions before placing an order. Your purchase includes 365 days of free updates, and you can extend the update service after expiration at a 50% discount.

If you take the corresponding PRINCE2-Practitioner exam within 60 days of purchase and do not pass, you may apply for a full refund under the 100% Money Back Guarantee. Claims based on an exam taken within 3 days of purchase are not eligible; free materials, expired orders, and downloaded products that were not used before sitting for the exam are also excluded. The candidate name must match the payer name.

To apply, submit a scanned enrollment slip and the official Score Report PDF within 2 days after the exam. Eligible requests are processed within 7 days. If you prefer an alternative, you may receive two free products of equal value and keep the update service for your original purchase.

Delivery is instant after payment. Your download is also sent to your email within one minute; if it has not arrived within 2 hours, contact customer service. There is no limit on the number of computers on which the material can be installed.

The published PRINCE2 Practitioner outline contains 4 major domains. The opening domains include:

  • PRINCE2 Practices (50%)
  • PRINCE2 Processes (25%)
  • PRINCE2 Principles (15%)

Review the complete Exam Topics section above for every domain and subtopic before planning your study time.

PRINCE2 Practitioner Sample Questions:

The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?

  • A. No, because the project manager should ensure that the change control approach is tailored to the project.
  • B. Yes, because the project should verify that the recorded status reflects the actual status of the products.
  • C. No, because the issue management and change control procedures can be treated as separate, but related, procedures.
  • D. Yes, because the change control approach should specify how the configuration item records are approved.
Reveal Solution  Discussion  0

Correct Answer: D  🗳️

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Risk tolerance heading?

  • A. The cost of all fallback plans must be contained within the project's tolerance.
  • B. Corporate management's threshold level of risk exposure is any combination of high and very high impact and probability.
  • C. The Project Board's threshold level of risk exposure is any combination of medium, high and very high impact, with high and very high probability.
  • D. The Project Manager's threshold level of risk exposure is low impact and probability.
  • E. The risk budget will have a tolerance of +/~ 10%.
Reveal Solution  Discussion  0

Correct Answer: A,C  🗳️

Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
A construction company that is one of ABC Company's key clients has agreed to provide a member of the staff to review and comment on the 'e-learning course'.
Which stakeholder interest should the member of staff represent, and why?

  • A. User, because this stakeholder ensures that the project provides value for money.
  • B. Supplier, because this stakeholder provides the expertise required by the project.
  • C. User, because this stakeholder may train its staff using the 'e-learning course'.
  • D. Supplier, because this stakeholder is an external supplier.
Reveal Solution  Discussion  0

Correct Answer: A  🗳️

Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
At the end of stage 2, the specialist 'e-learning course' supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier' s standards and techniques.
Is this appropriate, and why?

  • A. No, because the quality management approach should be created during the initiation stage and updated later.
  • B. Yes, because the quality management approach should take into account the supplier's standards, tools and techniques.
  • C. Yes, because the product description for each product will define the required quality approach within each stage.
  • D. No, because the quality management approach should be limited to ABC Company's quality standards.
Reveal Solution  Discussion  0

Correct Answer: B  🗳️

Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Monitoring and control section?

  • A. Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is produced at the end of each stage to identify any variations between planned status, reported status and actual status of the stage's products.
  • B. No change to entry 12 because this describes how the Project Board will control the stage.
  • C. Delete entry 13 because this is part of the Controlling a Stage process.
  • D. Move entry 12 because the Highlight Reports are deliverables of this stage and should be shown under Product descriptions.
  • E. Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not the Stage Plan.
Reveal Solution  Discussion  0

Correct Answer: B,E  🗳️

1053 Customer ReviewsCustomers Feedback (* Some similar or old comments have been hidden.)

I got 96% marks in the PRINCE2-Practitioner exam. I studied for the exam from the pdf dumps by Actual4dump. Amazing work done by team Actual4dump. Suggested to all.

Elma

Elma     5 star  

After praparation for one week, i was ready to rock my exam day and successfully passed the exam. Everything went well. Thanks for so helpful PRINCE2-Practitioner exam materials!

Clement

Clement     4 star  

When I was torn badly in work and studies for the exam PRINCE2-Practitioner , my friend saved me from getting in depression by suggesting to me Actual4dump guide as the most workable solution to my Amazing braindumps!

Marguerite

Marguerite     4 star  

For me I got all I wanted from PRINCE2-Practitioner study guide. I didn’t even need any other study material and passed the PRINCE2-Practitioner exam easily.

Jay

Jay     4.5 star  

Latest dumps for crtified PRINCE2-Practitioner exam at Actual4dump. I got 92% marks studying and preparing with them. Thank you so much Actual4dump for the updated files.

Belle

Belle     4 star  

Every certification exam means one step ahead in your career and I made progress in my career only with the help of Actual4dump 's study guide, dumps and practice tests. Hassle free solution to Ace Exam PRINCE2-Practitioner!

Les

Les     4.5 star  

Very updated exam guide by Actual4dump for PRINCE2-Practitioner certification. Helped me secure 96% marks in the exam. Looking forward to using Actual4dump for other exams as well.

Murphy

Murphy     4.5 star  

I got free update for PRINCE2-Practitioner exam dumps, and they were quite convenient.

Ferdinand

Ferdinand     5 star  

Anyway, I passed this PRINCE2-Practitioner exam.

Fabian

Fabian     5 star  

I can say with certainty that Actual4dump will help you pass PRINCE2-Practitioner exam.

Elliot

Elliot     5 star  

Best exam guide by Actual4dump for PRINCE2-Practitioner exam. I just studied for 2 days and confidently gave the exam. Got 93% marks. Thank you Actual4dump.

Nicola

Nicola     4 star  

Luckily, most of the questions in my exam are from your PRINCE2-Practitioner study materials. I passed my exam today easily. I will recommend your website- Actual4dump to all the people that I know!

Gale

Gale     5 star  

I passed the two exams.

Walter

Walter     4.5 star  

I study PRINCE2-Practitioner exam for three monthes and used your material to make sure get the cetification,you never let me down,thank you!

Andre

Andre     5 star  

PRINCE2-Practitioner exam used to be always tough! But i have passed it only after using PRINCE2-Practitioner exam dump! Come on, buy it and you will know how good it is!

Monroe

Monroe     5 star  

Now, i have finished my PRINCE2-Practitioner exam and pass with high mark. I really appreciate for the help of this Actual4dump dump. Thanks a lot.

Merlin

Merlin     4.5 star  

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Related Exams

Related Posts

Instant Download PRINCE2-Practitioner

After Payment, our system will send you the products you purchase in mailbox in a minute after payment. If not received within 2 hours, please contact us.

365 Days Free Updates

Free update is available within 365 days after your purchase. After 365 days, you will get 50% discounts for updating.

Porto

Money Back Guarantee

Full refund if you fail the corresponding exam in 60 days after purchasing. And Free get any another product.

Security & Privacy

We respect customer privacy. We use McAfee's security service to provide you with utmost security for your personal information & peace of mind.