
Free PMI-RMP braindumps download (PMI-RMP exam dumps Free Updated Jun 22, 2024)
PMI-RMP Dumps for Pass Guaranteed - Pass PMI-RMP Exam 2024
PMI-RMP certification not only validates the knowledge and skills of a professional in risk management but also provides them with a competitive advantage in the job market. PMI Risk Management Professional certification is recognized by top organizations around the world and can lead to higher salaries and better job opportunities.
If you want to highlight your skills in identifying and assessing project risks, mitigating threats, and capitalizing on opportunities, the PMI Risk Management Professional certification is ideal for you. Obtaining this certificate places you aside from other specialists and brings honor to your organization. All you have to do is pass the associated exam, which is PMI-RMP. Thus, if you’re waiting for greater recognition, this test will evaluate your expertise and help you stand out to the stakeholders, peers, and employers.
PMI-RMP certification exam covers various aspects of risk management, including identifying, assessing, and mitigating risks in projects. It also covers risk response planning, risk monitoring and control, and risk communication. PMI-RMP exam is designed to test an individual's ability to apply risk management principles and techniques in real-world scenarios. The PMI-RMP certification is ideal for professionals who work in project management, risk management, business analysis, or any other related field. It is also suitable for individuals who want to enhance their career prospects and increase their earning potential in the industry.
NEW QUESTION # 12
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
- A. The events should continue on with quantitative risk analysis.
- B. The events should be determined if they need to be accepted or responded to.
- C. The events should be entered into the risk register.
- D. The events should be entered into qualitative risk analysis.
Answer: C
NEW QUESTION # 13
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
- A. How the response will affect the quality of the components
- B. Verify due dates for the actions have been identified
- C. If the risk response is tied to an activity on the critical path
- D. Probability of a response triggering a secondary risk
Answer: B
Explanation:
Explanation
The first element the risk owner should look for in the response plan is to verify that due dates for the actions have been identified. This ensures that risk mitigation actions are timely and can be effectively monitored.
NEW QUESTION # 14
Who is the most appropriate person to conduct a risk identification brainstorming session?
- A. Subject matter expert
- B. Project manager
- C. Facilitator
- D. Project sponsor
Answer: C
NEW QUESTION # 15
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
- A. Discuss the risk response strategies with the stakeholders.
- B. Add buffers to the schedule to accommodate risk.
- C. Develop a communication plan to share updates on risks.
- D. Ensure the risk register includes all identified risks.
Answer: C
Explanation:
Explanation
The project manager should discuss the risk response strategies with the stakeholders to handle their expectations. This will help the project manager to align the risk responses with the stakeholder's risk appetite, preferences, and expectations. It will also help the project manager to obtain the stakeholder's support and approval for the risk responses. This is the best way to ensure clear visibility on the project risks and progress.
Adding buffers to the schedule to accommodate risk (option A) is not a good practice, as it may create false expectations and hide the true impact of risk. Ensuring the risk register includes all identified risks (option B) is important, but it is not enough to handle stakeholder expectations. The project manager also needs to communicate the risk register to the stakeholders and discuss the risk responses with them. Developing a communication plan to share updates on risks (option D) is also a good practice, but it is not sufficient to handle stakeholder expectations. The project manager also needs to involve the stakeholders in the risk response planning process and obtain their feedback and approval. References: PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 97; PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th ed., 2017, p. 407.
The project manager should develop a communication plan to share updates on risks (D) to handle stakeholder expectations, especially since the organization has a low risk appetite and stakeholders are very engaged. This approach ensures that stakeholders are regularly informed about the project's risks and progress, addressing their concerns and expectations. This is supported by the PMI's PMBOK Guide, Sixth Edition.
NEW QUESTION # 16
CORRECT TEXT
Fill in the blank with an appropriate phrase. The _________ is the risk or danger of an action or an event, a method or a (technical) process that still conceives these dangers even if all theoretically possible safety measures would be applied.
Answer:
Explanation:
residual risk
NEW QUESTION # 17
Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?
- A. Quantitative risk analysis process will be completed again after the plan risk response planning and as part of procurement.
- B. Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.
- C. Quantitative risk analysis process will be completed again after the cost management planning and as a part of monitoring and controlling.
- D. Quantitative risk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
Answer: B
NEW QUESTION # 18
In the country where a project is being executed, customs procedures are complex and change frequently.
During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?
- A. Low probability/low impact
- B. High probability/low impact
- C. High probability/high impact
- D. Low probability/high impact
Answer: C
NEW QUESTION # 19
Joan is the project manager of the KYU project for her company. She is working with management on defining a contingency reserve for her project. Currently the project is scheduled to last 18 months and it has a cost budget of $2.5 million. What two areas of the project can the contingency reserve address in regard to risk management?
- A. Risk and project planning
- B. Costs and schedule
- C. Quality and costs
- D. Cost and resource management
Answer: B
NEW QUESTION # 20
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?
- A. Corrective action
- B. Earned value management
- C. Technical performance measurement
- D. Risk audit
Answer: A
NEW QUESTION # 21
A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?
- A. Add the identified risk to the low-level risk watchlist.
- B. Add the identified risk to a quality control management control chart.
- C. Add the identified risk to the issues log.
- D. Add the identified risk to the risk register.
Answer: D
NEW QUESTION # 22
Della works as a project manager for SoftTech Inc. She is working with the project stakeholders to begin the quantitative risk analysis process. Which of the following inputs will be needed for the quantitative risk analysis process in her project? Each correct answer represents a complete solution. Choose all that apply.
- A. Risk register
- B. Risk management plan
- C. Cost management plan
- D. Project scope statement
Answer: A,B,C
NEW QUESTION # 23
Which types of project tends to have more well-understood risks?
- A. First-of-its kind technology projects
- B. Recurrent projects
- C. State-of-art technology projects
- D. Operational work projects
Answer: B
NEW QUESTION # 24
An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.
What should the risk management team leader do in the early stages of the project?
- A. Conduct qualitative risk analysis to prioritize potential risks.
- B. Benchmark to an organization which has executed a similar project,
- C. Educate stakeholders on best practices to perform risk management.
- D. Plan a solid risk response plan and secure the necessary funding.
Answer: C
Explanation:
Explanation
In the early stages of a project, the risk management team leader should conduct qualitative risk analysis to prioritize potential risks. This will help the team to focus on the most significant risks and develop appropriate risk response strategies.
According to the PMI-RMP Handbook, the early stages of the project are the best time to establish the risk management plan, which is a document that describes how risk management activities will be structured and performed on the project. It is one of the main outputs of the Plan Risk Management process. The risk management plan should be developed with the involvement and input of key stakeholders, such as the project sponsor, customer, team members, subject matter experts, and other relevant parties. The risk management plan should also define the roles and responsibilities of the stakeholders in risk management, as well as the reporting and escalation mechanisms.
The risk management team leader, who is a risk management certified candidate in their domain, should educate stakeholders on best practices to perform risk management in the early stages of the project. This is because the stakeholders may have different levels of knowledge, experience, and expectations regarding risk management, especially in an organization that spans across different countries. The risk management team leader should provide training, coaching, and guidance to the stakeholders on how to apply the risk management processes, tools, and techniques, as well as how to use the risk management plan. The risk management team leader should also promote a positive risk culture and encourage stakeholder participation and collaboration in risk management activities.
The other options are not valid for what the risk management team leader should do in the early stages of the project:
Conduct qualitative risk analysis to prioritize potential risks: This is not a valid option because the qualitative risk analysis is part of the Perform Qualitative Risk Analysis process, which comes after the Identify Risks process and before the Perform Quantitative Risk Analysis process. The risk management team leader should not conduct the qualitative risk analysis before developing the risk management plan and identifying the risks.
Plan a solid risk response plan and secure the necessary funding: This is not a valid option because the risk response plan is part of the Plan Risk Responses process, which comes after the Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis processes. The risk management team leader should not plan the risk response plan and secure the necessary funding before developing the risk management plan, identifying, and analyzing the risks.
Benchmark to an organization which has executed a similar project: This is not a valid option because benchmarking is a technique for risk identification, but it is not the only one. The risk management team leader should use a combination of techniques to identify risks, not just focus on one aspect. Also, benchmarking is not the same as educating stakeholders, which implies providing training, coaching, and guidance on risk management best practices.
References: PMI-RMP Handbook1, PMBOK Guide2, Practice Standard for Project Risk Management2
NEW QUESTION # 25
Management has asked you to perform a risk audit and report back on the results. Bonny, a project team member asks you what a risk audit is. What do you tell Bonny?
- A. A risk audit is a review of all the risks that have yet to occur and what their probability of happening are.
- B. A risk audit is an audit of all the risks that have occurred in the project and what their true impact on cost and time has been.
- C. A risk audit is a review of the effectiveness of the risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process.
- D. A risk audit is a review of all the risk probability and impact for the risks, which are still present in the project but which have not yet occurred.
Answer: C
NEW QUESTION # 26
Which of the following describes a difference between qualitative and quantitative risk analysis?
- A. Quantitative risk analysis prioritizes individual risks for subsequent treatment, qualitative risk analysis leads to quantitative risk analysis.
- B. Qualitative risk analysis addresses individual risks descriptively; quantitative risk analysis predicts likely project outcomes based on combined effects of risks.
- C. Quantitative risk analysis addresses individual risks descriptively; qualitative risk analysis predicts likely project outcomes based on combined effects of risks.
- D. Quantitative risk analysis adds to the risk register, qualitative risk analysis leads to quantitative risk analysis.
Answer: B
NEW QUESTION # 27
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
- A. Perform a SWOT analysis
- B. Develop an affinity diagram
- C. Assign probability and impact
- D. Perform the analytical hierarchy process
Answer: B
Explanation:
Explanation
An affinity diagram is a tool used to visually organize and group risks or ideas based on their similarities and categories. It helps in structuring the risks for further analysis and discussion. (Reference: PMBOK Guide, 6th Edition, p. 138) According to the PMBOK Guide, an affinity diagram is a tool and technique for the identify risks process that allows large numbers of ideas to be sorted into groups for review and analysis. An affinity diagram can help the risk manager to visually organize the risks identified in the pre-workshop survey by grouping them into categories based on their similarities or common characteristics. This can help the risk manager to facilitate the risk analysis and prioritization in the workshop, as well as to stimulate new patterns of thinking and generate additional risks.
Some of the other options are not relevant or appropriate for the question scenario:
The analytical hierarchy process is a technique for the plan risk management process that provides a method for comparing and ranking alternatives based on multiple criteria. It is not a tool for visually organizing risks.
A SWOT analysis is a technique for the identify risks process that examines the project from the perspective of its strengths, weaknesses, opportunities, and threats. It is not a tool for visually organizing risks, but rather for generating them.
Assigning probability and impact is a technique for the perform qualitative risk analysis process that assesses the likelihood and the potential effect of each individual risk on the project objectives. It is not a tool for visually organizing risks, but rather for evaluating them.
References: PMBOK Guide, 6th edition, pages 397-399, 414-415, 431-432, 441-442; PMI-RMP Exam Content Outline, 2015, page 7.
NEW QUESTION # 28
You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?
- A. Parkinson's Law
- B. Lag Time
- C. Avoidance
- D. Mitigation
Answer: C
NEW QUESTION # 29
......
Verified PMI-RMP dumps Q&As - Pass Guarantee Exam Dumps Test Engine: https://www.actual4dump.com/PMI/PMI-RMP-actualtests-dumps.html
Verified PMI-RMP dumps and 133 unique questions: https://drive.google.com/open?id=1bRP9lwDQ9SpxLQtnxM2PL5YyygGB7tVj