NEW QUESTION 27
A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?
- A. Change the special procurement key of the phantom assembly in the BOM.
- B. Change the item category of the phantom assembly in the BOM.
- C. Change the explosion type of the phantom assembly in the BOM.
- D. Change the phantom item indicator for the phantom assembly in the BOM.
Answer: C
NEW QUESTION 28
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Creation of a purchasing contract
- B. Change of the material'sprocurement type
- C. Creation of dependent requirements
- D. Change of the storage bin
- E. Creation of a sales order
Answer: B,C,E
NEW QUESTION 29
How can you set up the supply source for the SAP Kanban process? Note: There are 3correct answers to this question.
- A. Using purchasing costs for automated source prioritization
- B. Using quotations for internal and external procurement
- C. Using stock transfer reservations for stock transfer
- D. Using run schedule quantities for in-house production
- E. Using purchase orders for external procurement
Answer: C,D,E
NEW QUESTION 30
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Full conversion
- B. Partial conversion
- C. Individualconversion
- D. Order release
Answer: A,B
NEW QUESTION 31
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a negative offset time in the strategy profile.
- B. Specify a positive planning horizon in the strategy profile.
- C. Specify a negative planning horizon in the strategy profile.
- D. Specify a positive offset time in the strategy profile.
Answer: A
NEW QUESTION 32
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.
- A. Material Requirements Planning (MRP)
- B. Integrated Business Planning (IBP)
- C. Supply Chain Management (SCM)
- D. Capacity Requirements Planning (CRP)
Answer: B,C
NEW QUESTION 33
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.
- A. In the MRP controller
- B. In the production order type
- C. In the production version
- D. In the routing
- E. In the bill of materials (BOM)
Answer: A,B,D
NEW QUESTION 34
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Backflushing
- B. Transfer Order
- C. Kanban
- D. Picking list
Answer: D
NEW QUESTION 35
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planned order's components are copied from the picking list.
- B. The planned order is converted to a production order.
- C. The planned order generates capacity requirements.
- D. The planned order's component availability is checked
Answer: C
NEW QUESTION 36
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.
- A. Engineering change management
- B. Planning
- C. Inspection during production
- D. Implementation
Answer: B,D
NEW QUESTION 37
What is the difference between co-products and by-products?
- A. Only by-products have a zero inventory valuation.
- B. Only co-products are identified by a special item category in the bill of material (BOM).
- C. Only co-products appear in the processor production order settlement rule.
- D. Onlyco-products can be manufactured in isolation from the main product.
Answer: C
NEW QUESTION 38
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.
- A. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
- B. Add the agreement to the source list and mark itfor MRP relevance.
- C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- D. Add the agreement to the quota arrangement and mark it for MRP relevance.
Answer: B,C
NEW QUESTION 39
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. The Change Planning Direct on indicator is set.
- C. Alternative resources are fully occupied.
- D. The work center has several individual capacities.
Answer: A,D
NEW QUESTION 40
What is a work center hierarchy in SAP S/4HANA capacity planning?
- A. A group of alternative work centers for production, structured in hierarchy levels by prior ties
- B. A group of alternative work centers providing a cumulative available capacity for production
- C. A group of work centers in a production line beingused in sequence for production
- D. A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
Answer: B
NEW QUESTION 41
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
- A. Make-to-order production (20)
- B. Make-to-stock production (10)
- C. Planning without final assembly (50)
- D. Planning with final assembly (40)
Answer: D
NEW QUESTION 42
Duringproduction order creation, several valid production versions are found. How does the system choose the product conversion?
- A. Lot size or material cost
- B. Planned order or materialnumber
- C. Validity period or sales order
- D. Alphanumeric or quota arrangement
Answer: D
NEW QUESTION 43
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.
- A. In-house production time
- B. Planned delivery time
- C. Operation duration
- D. Total replenishment lead time
Answer: A,B
NEW QUESTION 44
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
- A. Material Requirements Planning (MRP)
- B. Capacity Requirements Planning (CRP)
- C. Demand Planning (DP)
- D. Supply Network Planning (SNP)
Answer: A
NEW QUESTION 45
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. To determine the work in progress along the production line
- B. To provide timely updates of inventory management for the staged components
- C. To reduce the totalproduction lead time for along production line
- D. To stage different components for a production line simultaneously
Answer: A,B
NEW QUESTION 46
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?
- A. Use a heuristic.
- B. Use a propagation range.
- C. Use a planning group.
- D. Use a resource group.
Answer: A
NEW QUESTION 47
......
SAP S/4HANA Production Planning and Manufacturing Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Lean Manufacturing in SAP S/4HANA | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Introduction to SAP S/4HANA Production Planning | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Advanced Planning in SAP S/4HANA | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Introduction to SAP S/4HANA Supply Chain Planning | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Master Data in SAP S/4HANA | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Capacity Planning in SAP S/4HANA | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Material Requirements Planning in SAP S/4HANA | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Demand Management in SAP S/4HANA | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Process Orders in SAP S/4HANA | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Production Orders in SAP S/4HANA | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
SAP S/4HANA Production Planning and Manufacturing Certification Exam Details:
| Passing Score | C_TS422_2020 - 56% C_TS422_1909 - 55% |
| Exam Price | $550 (USD) |
| Exam Name | SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing |
| Level | Associate |
| Schedule Exam | SAP Training |
| Duration | 180 mins |
| Exam Code | C_TS422_2020 |
| Number of Questions | 80 |
| Reference Books | TS421, TS422 (SAP S/4HANA 2020) TS421 (SAP S/4HANA 1909), TS422 (SAP S/4HANA 1909) |
| Sample Questions | SAP S/4HANA Production Planning and Manufacturing Certification Sample Questions |
SAP C-TS422-2020 Test Engine PDF - All Free Dumps: https://www.actual4dump.com/SAP/C-TS422-2020-actualtests-dumps.html